Base build Electrical works Embassy Crest for Mercedes Benz- Bangalore

Site Kolar, Karnataka
Capacity 2 x 1.7MVA System
Client ANL (Consortium of Embassy group & UTL group) , Bangalore
Scope of work EPC works for building base build works.
Power Evacuation 2 x 11kV line from BESCOM.
Project duration Seven months from order receipt. COD – April 2015.
Technical particulars Transformer – VOLTAMP, 1700KVA x 2. HT panel –Lotus switch gears, Schneider breakers. LT Panel – SV Karanth

Base build and Interior Electrical works Karbonn Mobiles Manufacturing unit- Tirupati

Site Tirupati, Andhra.
Capacity 1,00,000 sqft of Mobile manufacturing unit.
Client United Teli-Links , Bangalore.
Scope of work Supply, Installation, testing and commissioning of 11kV HT Panel, 500kVA Transformer, LT Switch gears and lower side electrical equipment and works.
Power Evacuation At 11kV From APSPDCL substation at Renigunta .
Project duration 6 months from the date of commencement. COD Feb 2018.
Current status Operational.
Technical particulars Power Transformer – Vijaya Transformers , 500kVA x 1. HT Panel– Lotus switchgears(11KV), ABB Breakers. LT Panel – Bhaskara Power / SV Karanth. (Schneider make LV Breakers)